C-65.1, r. 5 - Regulation respecting construction contracts of public bodies

Full text
46. If the public body and the contractor cannot agree on the value of a change at the first negotiation, the detailed estimate of the change required is then determined by the public body and paid according to the conditions stipulated in the contract.
O.C. 532-2008, s. 46.